Jahan Aray Complex

Completed projectsShoring

Shoring | Drainage and Insulation

  • Client Absa Construction company
  • E.P.C Contractor Baspar Pey Iranian company
  • Location Tehran, Iran
  • Start Date October 2021
  • Shoring Method Nailing & Anchorage
  • Excavation Depth 40 m
  • Stabilized Area 7,775 m2
  • Total Nailing & Anchorage Length 23,632 m
  • Steel Structure Weight 500 Ton
  • Execution Period 382 days