Mika Knots Building

Completed projectsShoring

Shoring | Drainage and Insulation

  • Client MIKA Construction Group
  • Consultant Soroush Darya Pey company
  • E.P.C Contractor Baspar Pey Iranian company
  • Location Tehran, Iran
  • Start Date August 2018
  • Shoring Method Nailing & Anchorage
  • Excavation Depth 40 m
  • Stabilized Area 3,789 m2
  • Total Nailing & Anchorage Length 22,678 m
  • Steel Structure Weight 156 Ton
  • Total Soil Excavation Volume 37,812 m3
  • Execution Period 195 days