Atiyeh Gharb Hospital

Completed projectsShoring

Shoring | Drainage and Insulation

  • Client Tolou Atiyeh Gharb company
  • Consultant Gorouh-e-Chahar Consulting Engineers
  • Client’s Supreme Consultant Pars GeoEnviro Consulting Engineers
  • E.P.C Contractor Baspar Pey Iranian company
  • Location Tehran, Iran
  • Start Date July 2014
  • Shoring Method Nailing & Anchorage
  • Excavation Depth 40 m
  • Stabilized Area 12,300 m2
  • Total Nailing & Anchorage Length 71,500 m
  • Total Berliner Columns Length 1,058 m
  • Execution Period 40 days