Saman Faraz Towers

Completed projectsSoil Improvement

Execution of structural concrete piles

  • Client Behnad Bana Construction company
  • Consultant Tadbir Sahel Pars company
  • E.P.C Contractor Baspar Pey Iranian company
  • Location Tehran, Iran
  • Start Date June 2018
  • Shoring Method Nailing & Anchorage
  • Excavation Depth 35 m
  • Stabilized Area 11,935 m2
  • Total Nailing & Anchorage Length 34,996 m
  • Total Length of Concrete Piles & Soldiers 1,525 m
  • Total Soil Excavation Volume 215,000 m3
  • Soil Improvement Method concrete piles
  • Total Volume of Soil Improvement 1,750 m3
  • Execution Period 365days